Inspection of brine pipeline bridge Gosauzwang

Inspection of brine pipeline bridge Gosauzwang

Bridges

Building category

Steel construction

Construction method

Building inspection

Performed services

Inland

Region

June 2025

Processing time from

January 2026

Processing time until

DI Georg Wallner

Project manager

DI Marina Gschwendtner

Substitute project manager

DI Walter Reisenauer

Project team member

Salinen Austria AG

Client

Frame bridges, steel composite

Type of bridge

6

Number of fields

21,00 m

Maximum span

125,00 m

Length of bride

241,00 m²

Expanse of bridge

Description of project

The brine pipe bridge Gosauzwang connects the towns of Hallstatt and Gosau in Austria. The pillars are up to 30 meters high and were built around 1758. Today, they carry an aluminium lattice construction which is used as a pedestrian and cyclist bridge. In 2017 the bridge became a listed construction.

Our office was commissioned with the constructional inspection and recalculation of the lattice for the reconstruction of the pipeline in 2025.

Description of tasks

  • In-situ inspection
  • Elaboration of inspection report including plans
  • Recalculation of bridge in its current state
  • Recalculation of bridge with additional load caused by the newly planned brine pipes (in different variations)

You would like to know more about our projects or you have detailed questions? Don’t hesitate and get in touch with us here.