Bridges, Infrastructure
Building category
Solid construction
Construction method
Detail planning, Planning of structural framework
Performed services
Inland
Region
May 2011
Processing time from
June 2011
Processing time until
DI Sascha Grujic
Project manager
Wildbach- und Lawinenverbauung Gebietsbauleitung Bludenz
Client
Integral bridges
Type of bridge
1
Number of fields
6,60 m
Maximum span
6,80 m
Length of bride
35,00 m²
Expanse of bridge
Description of project
In behalf of the torrents and avalanche control, section Bludenz, we worked out the detailed planning and supporting structure planning for two bridges across the Zürs-river.
- 2 integral bridges: length = 6.80 m, span length = 6.40 m, area = 35 m2
Description of tasks
- Site inspection and in-situ survey
- Structure planning and static calculations
- Detailed plans