Refurbishment Spar-vault/culvert, Flexen-ravine (A)

Tunnel

Building category

Solid construction

Construction method

Building inspection , Detail planning, Tender offer

Performed services

Inland

Region

September 2022

Processing time from

April 2025

Processing time until

DI Georg Wallner

Project manager

DI Stefan Gschwendtner

Substitute project manager

Bojana Panic

Project team member

Amt der Vorarlberger Landesregierung

Client

22,00 m

Length of tunnel

State road

Road networks

Description of project

The Spar-vault was built in 1935 as part of the Flexen-gallery on the L198 between Kloesterle and Lech am Arlberg. The County Government of Vorarlberg started refurbishment on the age-related damages at the vault/culvert in 2022.

The works included the restauration of the concrete damages, concrete spalling, reinforcement corrosion of the bridge vault, damages on the stone facing and on the front surface of the Spar-vault as well as rock extractions beneath the vault’s abutment. Furthermore, the culvert was stabilized.

Our office was commissioned with the project engineering of all building works.

Description of tasks

  • In-situ inspection and examination of structures
  • Elaboration of inspection report and tender documents
  • Elaboration of action plans and refurbishment plans
  • Drafting of location plan and traffic routing plan
  • Supervision during execution period regarding structural details

You would like to know more about our projects or you have detailed questions? Don’t hesitate and get in touch with us here.