Industrial- and commercial buildings
Building category
Timber construction, Solid construction, Steel construction
Construction method
Planning for submission, Building supervision, Planning of structural framework
Performed services
Inland
Region
May 2021
Processing time from
February 2023
Processing time until
DI Sascha Grujic
Project manager
DI Georg Wallner
Substitute project manager
DI Alexander Sparr, DI Alexander Grujic
Project team member
Adolf ERHART GmbH
Client
18.592,50 m³
Building volume
1.430,00 m²
Gross floor area
Description of project
The existing area of the sawmill hall at the Erhart Ltd in Sonntag (A) was covered with a new roof between May 2021 and February 2023 to guarantee premium handling of all sorts of timber. The hall is 40.20 m long and approximately 27 m wide with a ridge height of + 18.10 m. The foundation supports and eaves beams consist of ferroconcrete, the gable roof girders are made of glulam, the gable roof and wall constructions of timber. Stairs, handrails as well as gangways are steel constructions. A 10 tonnes indoor crane was installed for repair works on the saw. The erection of the indoor crane took place during normal operations above the old hall roofs, which were dismantled after the completion.
Description of tasks
- Structural calculations for the ferroconcrete-, steel- and timber building works according to current laws and regulations
- Application and execution planning
- Creation of reinforcement plans
- Construction supervision during project execution
You would like to know more about our projects or you have detailed questions? Don’t hesitate and get in touch with us here.