Annexe and alterations hotel Daneu

Industrial- and commercial buildings

Building category

Timber construction, Solid construction

Construction method

Planning of structural framework

Performed services

Inland

Region

February 2018

Processing time from

September 2018

Processing time until

DI Walter Reisenauer

Project manager

DI Sascha Grujic

Substitute project manager

Anja Dünser

Project team member

12.000,00 €

Project costs

Burtscher KG Hotel Daneu

Client

5.323,00 m³

Building volume

1.639,00 m²

Gross floor area

Description of project

The building works for the annexe at the hotel Daneu in Nueziders (A) was divided into:

  • Annexe north: 3-storey annexe as solid construction (ferroconcrete, bricks and steel stanchions). A storage room and a bikeport were built in the basement, on the ground floor a reefer and a kitchen extension. Additional hotel rooms were realised on the upper floor of the annexe north.
  • Annexe west: 2-storey annexe, basement as solid construction (ferroconcrete and steel stanchions), ground floor partially solid construction respectively timber work. In the basement new hotel rooms were built and on the ground floor a dining hall as well as a patio.
  • Alteration works in three storeys as steel and solid construction (ferroconcrete and steel stanchions/girders) – replacement respectively underpinning at cut-outs and door/window enlargements.

Description of tasks

  • Structural supervision of solid construction from concept to finish
  • Structural supervision of timber construction from concept to finish
  • Planning of structural framework
  • Reinforcement drawings, steel and timber building specifications/plans

You would like to know more about our projects or you have detailed questions? Don’t hesitate and get in touch with us here.