Planning of torrent barrier Balbier river, St. Gallenkirch (A)

Protective structures, Underground- and hydraulic structures

Building category

Solid construction

Construction method

Detail planning, Planning of structural framework

Performed services

Inland

Region

October 2011

Processing time from

November 2010

Processing time until

DI Sascha Grujic

Project manager

Wildbach- und Lawinenverbauung Gebietsbauleitung Bludenz

Client

48,00 m

Length of crown dam

17,00 m

Height

Description of project

As commissioned by the torrents and avalanche protection office, section Bludenz, we prepared the detailed planning and the structure planning for the barrier in the Balbier river in St. Gallenkirch (total area 620 m2).

Description of tasks

  • site inspection and in-situ survey
  • structure planning and static calculations
  • elaboration of detailed plans