Protective structures, Underground- and hydraulic structures
Building category
Solid construction
Construction method
Detail planning, Planning of structural framework
Performed services
Inland
Region
July 2011
Processing time from
January 2012
Processing time until
DI Sascha Grujic
Project manager
Wildbach- und Lawinenverbauung Gebietsbauleitung Bludenz
Client
47,30 m
Length of crown dam
15,60 m
Height
Description of project
We made the detailed planning and the structure planning for two barriers (total area 840 m2) in the Meng-river, Nenzing, as commissioned by the torrents and avalanche protection office, section Bludenz.
Description of tasks
- Site inspection and in-situ survey
- Structure planning and static calculations
- Elaboration of detailed plans