New building of the safety centre Bad Goisern

Public buildings

Building category

Solid construction, System building construction

Construction method

Planning of structural framework

Performed services

Inland

Region

September 2015

Processing time from

January 2017

Processing time until

DI Georg Wallner

Project manager

DI Sascha Grujic

Substitute project manager

Anja Dünser

Project team member

2.375.000,00 €

Project costs

Gemeinde Bad Goisern

Client

Description of project

The building consists of a one-storey vehicle hall for the fire brigade (l/w/h = aprrox. 31m/20m/5.50m - 6.80m), a hose tower (h = approx. 12m) and a two-storey area (head-end structure) with garages for the water- and mountain rescue and other rooms (in total l/w/h = approx. 27m/14.50m/6m - 7.20m). The difference in width between the two buildings is connected by a 4.50 m projecting canopy.

The building was mainly erected as reinforced concrete structure with semi-finished parts. The large span lengths of the vehicle hall were traversed by hollow core slabs.

A difficult task was the big size of the projecting canopy, in which the reinforced concrete ceiling and the hollow core slabs converge. Owing to the chosen solution a harmonic deformation pattern could be found.

Description of tasks

  • Planning and calculation of the solid construction with single steel girders
  • Elaboration of a solution for the projecting canopy with steel girders, which serve as a support for the hollow core slab and to which the reinforced concrete ceiling (element slab) connects

You would like to know more about our projects or you have detailed questions? Don’t hesitate and get in touch with us here.