Construction of new commercial building Scheuchl

Industrial- and commercial buildings

Building category

Solid construction

Construction method

Detail planning, Building supervision, Planning of structural framework, Tender offer

Performed services

Inland

Region

July 2015

Processing time from

December 2016

Processing time until

DI Sascha Grujic

Project manager

Alexander Sparr

Substitute project manager

Alexander Grujic, DI Georg Wallner

Project team member

1.200.000,00 €

Project costs

Scheuchl Transporte GmbH

Client

6.332,40 m³

Building volume

891,80 m²

Gross floor area

Description of project

The vehicle hall with approx. 56 m length, 18 m depth and 6.50 m height is divided in seven parking bays (of which four can be served by a 5-tons indoor crane) and a washing box. A projecting awning of 2.60 m is situated above the entrance gates.

The base plate and the walls are made of in-situ concrete, the flat roof was built as a hollow core slab. The awning is carried out as a steel construction.

During the planning works the requirements of the torrents and avalanche protection office had to be taken into account in regard of pressures resulting of avalanches (i.e. impact load and snow pressure on the uphill walls, additional snow loads on the roof including the awning).

Description of task

  • Application plans
  • Call for tender and construction supervision
  • Detailed planning
  • Structural design of the builing from concept to completion

You would like to know more about our projects or you have detailed questions? Don’t hesitate and get in touch with us here.