Crane girder bridge Sonntag

Bridges

Building category

Timber construction, Steel construction

Construction method

Detail planning, Planning of structural framework

Performed services

Inland

Region

April 2014

Processing time from

July 2014

Processing time until

DI Sascha Grujic

Project manager

DI Georg Wallner

Substitute project manager

Gemeinde Sonntag

Client

Frame bridges

Type of bridge

1

Number of fields

24,00 m

Maximum span

27,60 m

Length of bride

36,43 m²

Expanse of bridge

Description of project

The old Reutele-Bridge was destroyed at the flood in August 2005. Therefore the erection of a new bridge in consideration of the updated flood flows was necessary. The characteristic of the hiking bridge across the Lutz in the municipality of Sonntag is that it is made of three crane girder parts of a tower crane, which are joined with plug connections common in crane construction. Through additional diagonals at the girder joints and strengthening at the bridge supports it was possible to adapt the framework of the crane girders in a way to create a fully adequate pedestrian bridge.

Bridge details:

  • Footbridge range 24.00 m
  • Overall length 27.60 m
  • Width 1.20 m
  • Area 33.12 m²

Description of tasks

  • Calculation and dimensioning of the support structure
  • Detailed planning of the bridge including reinforcement measures and adaption for installation of railings and surface
  • Detailed planning of the required adaption of the abutment, which was prepared with mortared stone layers in the course of the bank protection works