Erhart Ltd Timber, new workshops and storehouse incl. passengers’ and goods’ lift

Industrial- and commercial buildings

Building category

Timber construction, Solid construction, Steel construction, Composite construction

Construction method

Planning for submission, Building supervision, Energy performance certificate

Performed services

Inland

Region

October 2022

Processing time from

December 2024

Processing time until

DI Alexander Sparr, DI Walter Reisenauer

Project manager

DI Sascha Grujic

Substitute project manager

DI Georg Wallner, Alexander Grujic, Laetitia Elsener, DI Stefan Gschwendtner

Project team member

Adolf ERHART GmbH

Client

8.096,00 m³

Building volume

1.673,00 m²

Gross floor area

Description of project

In the years 2022 until 2024 the Erhart Ltd, Sonntag (A), erected a new building for workshops and storage space on their premises. In this building are situated: a locksmith-workshop including an indoor crane and a service pit, an office for staff members, a locker room, toilet facilities and several storerooms. The building has four floors and an overall height of approx. 18 m. The effective area sums up to 1,380 m2. The basement, the elevator shaft, the ground floor base plate and the walls on the ground floor were built in ferroconcrete style. The suspended ceilings, outer and inner walls on the upper floors as well as the flat roof were realized as a timber construction.

Description of tasks

  • Structural calculations and application planning for the ferroconcrete-, steel- and timber building works according to current laws and regulations
  • Creation of reinforcement plans
  • Drafting of energy performance certificate
  • Construction supervision during project execution

You would like to know more about our projects or you have detailed questions? Don’t hesitate and get in touch with us here.