Bridges, Infrastructure
Building category
Solid construction, Prestressed concrete
Construction method
Examination
Performed services
Inland
Region
January 2022
Processing time from
December 2022
Processing time until
DI Walter Reisenauer
Project manager
DI Sascha Grujic
Substitute project manager
DI Marina Gschwendtner
Project team member
ASFINAG Bau Management GmbH
Client
Culverts, Box girder bridges, T-beam bridges, Prestressed concrete bridge
Type of bridge
76
Number of fields
47,80 m
Maximum span
1.724,00 m
Length of bride
21.316,00 m²
Expanse of bridge
Motorway
Type of road
10.602,00 m
Length of road
Description of project
In 2022 we were commissioned by the ASFINAG to inspect the bridges, signposts and noise protection constructions on the A14.
19 bridges with a full surface of 21,316.0 m2
- 2 prestressed concrete bridges with a surface of 2,192.0 m2
- 17 ferroconcrete bridges with a surface of 19,124.0 m2
16 noise protection constructions and signposts, length = 10,602.0 m2
The inspection of the various bridges over the A14 could only take place at night, because one lane had to be shut during these hours. We were equipped with a lifting platform and a work platform.
Description of tasks
- Site inspection and survey of bridges and culverts with mapped and photographic documentation
- Elaboration of test reports including damage category
- Drafting of general plans and damage plans
- Measuring and calculation of bearing displacements
You would like to know more about our projects or you have detailed questions? Don’t hesitate and get in touch with us here.