ASFINAG, stress calculation for official approval water retention system 2015, ASFINAG

Underground- and hydraulic structures, Infrastructure, Watercourse protection facilities

Building category

Solid construction

Construction method

Expertise, Examination

Performed services

Inland

Region

January 2015

Processing time from

December 2015

Processing time until

DI Walter Reisenauer

Project manager

DI Sascha Grujic

Substitute project manager

ASFINAG Baumanagement GmbH

Client

Motorway

Type of road

311,00 m

Length of road

8.758,00 m²

Base area

Description of project

In 2015 we were commissioned to work out the structural analysis tests for the projects of the ASFINAG Alpenstraßen GmbH as follows:

2 motorway bridges (V50 and V51) with an overall area of 8.758 m2 and a total length of 311 m:

  • 2 loosely reinforced concrete bridges

Description of tasks

  • stress calculation for official approval of the water retention system Klaus, A14
  • stress calculation for official approval of the water retention system Wolfurt, A14
  • elaboration of detailed plans

You would like to know more about our projects or you have detailed questions? Don’t hesitate and get in touch with us here.