Underground- and hydraulic structures, Watercourse protection facilities
Building category
Solid construction
Construction method
Planning of structural framework
Performed services
Inland
Region
November 2019
Processing time from
July 2020
Processing time until
DI Georg Wallner
Project manager
DI Sascha Grujic
Substitute project manager
Alexander Grujic
Project team member
Kubisch Data GmbH / ASFINAG Bau Management GmbH
Client
9.932,00 m³
Volume
3.075,00 m²
Base area
3,23 m
Depth
Description of project
The watercourse protection facility no. III is built during the enlargement of the resting place Hainbach. This facility is situated between the A1, west-motorway, and the L1267, Auracher Straße. The reinforced concrete basin shows a trapezoidal floor plan with a length of approx. 80 m in west-east direction. The width sums up to approx. 55 m on the west side and 22 m on the east side. A maintenance path runs along the south side, parallel to the motorway and on the west side on level of the basin top. Furthermore, a maintenance area is planned on the east side about half way up the basin. The basin embeds between 3.50 m – 5.50 m underneath the existing terrain. It is divided by partition walls into upstream basin, main basin and discharge outlet. An exit ramp is situated on the south side.
Description of tasks
- Static and structural assistance during tender design
- Static and structural assistance during detailed planning
- Creation of reinforcement plans
You would like to know more about our projects or you have detailed questions? Don’t hesitate and get in touch with us here.