Asfinag, A01, lane Walserberg

Infrastructure

Building category

Miscellaneous

Construction method

Planning of structural framework, Tender offer

Performed services

Inland

Region

March 2021

Processing time from

July 2021

Processing time until

DI Rudolf Pernkopf

Project manager

DI Georg Wallner

Substitute project manager

DI Katharina Thomson, DI Angela Gratzer

Project team member

ASFINAG Bau Management GmbH

Client

Motorway

Type of road

Description of project

In 2021 we were assigned by ASFINAG Bau Management GmbH with the elaboration of the tender and the execution planning for the above mentioned project:

West motorway, km 292.35 - km 297.7, lane Walserberg; overhauling/replacement building noise prevention, blacktopping breakdown lane, superstructure refurbishment ramps 2 + 3 Wals, overhauling and reinforcement of bridges’ supporting structures

Description of tasks

  • Open land - blacktopping (5 cm), drafting pavement design specification breakdown lane, manoeuvre tracks, ramps, plan for traffic signs; superstructure refurbishment junction Salzburg West, ramps 2 and 3
  • Noise prevention walls – in-situ inspection, action planning for reconstruction and coffer change
  • Structural calculations, incorporation A01 design concept
  • Bridge A001.070+71 - structural calculations, planning reinforcement of supporting structure and new edge beams
  • Bridge A001.069 - structural calculations steel structure including foundation for erecting of noise protection walls
  • Bridge A001.064-067 – structural calculations re-anchoring of the edge beams from below

You would like to know more about our projects or you have detailed questions? Don’t hesitate and get in touch with us here.